The custom home building process in Texas
Building a custom home in Texas takes six stages: evaluating the land, drawing original plans, coordinating systems and interiors, preparing procurement and a work schedule, constructing the house and walking it at the end. Stein Meyer Hartmann Construction gives an estimated date for substantial completion once design and preconstruction are finished.
- What happens at the land stage?
- Who draws the plans?
- What is coordinated before construction?
- What do procurement and the work schedule deliver?
- How long does construction take?
- What is the final walkthrough?
1. What happens at the land stage?
We walk your land together. You receive our read of the access, the trees, the slope and the ground, including what could be hard. If you have not bought yet, this visit shows what the lot will ask of the house.
2. Who draws the plans?
Your architect draws original plans for your lot. The team you choose is described on the custom homes page. The deliverable is a set of architectural drawings made for your site and your family.
3. What is coordinated before construction?
Electrical, plumbing, heating and cooling and any smart home cabling are routed on the drawings, and interior details are settled with them. The deliverable is a coordinated plan set in which each system has a place. The method is explained in our guide to how to plan a custom home.

4. What do procurement and the work schedule deliver?
Before we order anything, we list the materials, name the source for each and estimate the cost. The deliverables are that list and a sequence of work built alongside the design. We sit down with you to discuss concerns or changes before ordering begins.
5. How long does construction take?
Every house differs, and the estimated date for substantial completion comes after design and preconstruction are complete. The length of construction depends on the house and its plans, so we do not quote a standard number of months. Early preparation prevents many change orders, but not all.
6. What is the final walkthrough?
At the final walkthrough we go through each room with you and list anything that is not right.
When do oak trees affect the schedule?
Texas A&M Forest Service advises against pruning or wounding oaks from February through June because of oak wilt. Work near mature oaks is scheduled around that season, which can shift when clearing and utility trenching happen.
Questions about the process
Why finish the drawings before construction starts?
A decision made on paper costs less than one made on site. We finish the drawings first, because moving a wall on a sheet takes minutes, while moving it after framing takes a crew. The sequence also lets each trade see the whole house before it begins.
Who is my contact during the build?
You deal with the people running your project, and you can raise a concern or a change at any time. We sit down together to discuss it, and the decision stays with you. Names and roles for the team appear on the about page.
Does a remodel follow the same stages?
It follows the same stages, with a survey of the existing house added at the start. The differences are set out on our page about luxury remodeling, including how a family can stay in the house between phases of the work.
Sources
Diagrams on this page are illustrations of the stages, not specific projects.
See where your project would start.
Tell us what you have in hand today. We will tell you which stage you are in and what comes next.